Short answer: In New Jersey, a generator that feeds your home's wiring needs listed transfer equipment, such as a transfer switch or a listed interlock, so it can never send power back onto the utility lines. It also needs a permit and an inspection.

This page explains the code basics in plain terms. It is part of our NJ electrical code library. It is not a how-to guide. Electrical work in NJ needs a permit and a licensed electrician, and the local inspector has the final say.

What is backfeeding, and why is it so dangerous?

Backfeeding means powering your house wiring by plugging a generator into a wall outlet, often with a double-male "suicide cord." The U.S. Consumer Product Safety Commission calls this extremely dangerous. It can electrocute utility workers and neighbors served by the same utility transformer. It also bypasses some of the home's built-in circuit protection.

PSE&G warns that backfeed puts utility workers, neighbors and your own household at risk of electrocution. It can also cause a fire or explosion. PSE&G says the generator owner is legally responsible for preventing it.

Line crews working during an outage may expect a line to be dead. A backfeeding generator can make it live without warning. That is why the code requires equipment that keeps the two power sources apart.

What does NEC 2023 Article 702 cover?

Article 702 covers optional standby systems. These are backup systems that are not required by law, like a home generator. New Jersey's updated codes, including the 2023 National Electrical Code, took effect August 17, 2026. A complete permit application submitted by February 17, 2027 can still be reviewed under the previous code.

NEC 2023 section What it covers In plain terms
702.4 Capacity The generator must be big enough for the loads it will carry.
702.5 Transfer and interconnection equipment Listed equipment must prevent the generator and utility from being connected together by accident.
702.7 Signs Warning signs identify the standby source, including a sign at a generator inlet.
702.12 Outdoor generator sets Rules for disconnects and for the inlet a portable generator plugs into.

702.5: Transfer equipment is required

To connect a standby system to a home's wiring, the code requires interconnection or transfer equipment. In the 2023 edition, this equipment must be listed. It must be designed and installed to prevent the inadvertent interconnection of all sources of supply. In short, the equipment must keep the generator from ever feeding the utility lines by accident.

A meter-mounted transfer switch, installed between the utility meter and the meter enclosure, must be a listed meter-mounted transfer switch and must be approved.

Transfer switch or interlock?

A transfer switch is a separate device that moves selected circuits from utility power to generator power. An interlock is a mechanical plate or slide on the panel. It keeps the main breaker and the generator breaker from being on at the same time.

Interlock kits are made for specific panel brands and models. Local building departments in NJ may ask for the manufacturer's specifications for the interlock device or transfer switch with the permit application. Whether a given kit is acceptable on your panel is up to the inspector.

Portable generator inlets

A portable generator usually connects through a power inlet, a fixed outdoor inlet box with male prongs that is wired to the transfer switch or interlocked breaker. For portable generators of 15 kW or less, the 2023 NEC adds that the flanged inlet or other cord-and-plug connection must be located outside the building. Inlets rated 100 amperes or more must be listed. If they are not rated as a disconnecting means, they need an interlocked disconnecting means.

702.4: Sizing and capacity

Sizing depends on how the loads are transferred:

  • Manual transfer (most interlocks and many portable setups): the user picks the loads. The generator must have enough capacity for everything intended to run at one time.
  • Automatic transfer: the 2023 NEC says the standby source must be capable of supplying the full load that is automatically connected. That load is figured using Article 220 or another method the inspector approves. A load management system can limit the load instead.

Your panel and service matter too. An old or full panel may not have space for a generator breaker or an interlock. Some homes need a panel upgrade or a sub panel first. Correct breaker sizing and grounding and bonding also apply.

702.7: Signs

Section 702.7 covers warning signs for standby systems. Where a power inlet is used for a portable generator, a warning sign must be placed near the inlet. It shows the type of generator that can be connected, based on how the transfer equipment is wired.

Do I need a permit in New Jersey?

Yes. Connecting a generator to a home's wiring is electrical work that needs a permit and inspection. Some NJ towns, for example Ringwood, ask for the construction permit forms, an electrical subcode form, a one-line wiring diagram with conductor and conduit sizes, and manufacturer specs for the transfer switch or interlock. That town also asks for panel and transfer switch covers to be off at inspection. Requirements vary by town, so check with your local construction office.

Carbon monoxide is the other major generator danger. CPSC says never run a generator inside a home, garage, basement, crawlspace or shed, even with doors open. Keep working CO alarms in the home. See our page on smoke and CO detector installation.

How Gareffa Electric can help

Gareffa Electric is a family-owned, licensed NJ electrical contractor (NJ Electrical Contractor License #18578), based in Nutley. We serve Bergen, Hudson, Essex and Passaic counties. We do not install generators, transfer switches or interlocks. We can help get your electrical system ready and safe:

Every job is permitted in our name and done by licensed electricians on our crew. We carry $2M in liability insurance, and a bond is available on request. Same-day or next-day dispatch is available, and we are often there within 2 to 4 hours of booking. A scheduled service call is $150 (diagnostic plus first hour, credited on jobs over $1,500). A same-day service call is $350. An estimate visit is free.

If there is smoke, fire or sparking that will not stop, leave the building and call 911.

FAQ

Is it legal to plug a generator into a wall outlet?

No. That is backfeeding. The NEC requires listed transfer equipment that prevents the generator and utility from connecting. CPSC calls backfeeding extremely dangerous, and PSE&G says the owner is legally responsible for preventing it.

Is a generator interlock kit allowed in NJ?

The 2023 NEC requires listed transfer equipment that prevents interconnection of sources. Interlock kits are made for specific panels. Your local inspector decides whether a kit is acceptable on your panel, and a permit is needed.

Which is better, a transfer switch or an interlock?

Both can meet the code when listed and installed correctly. The right choice depends on your panel, the loads you want, and what your inspector approves.

How big does my generator need to be?

With manual transfer, it must handle everything you plan to run at one time. With automatic transfer, it must carry the full automatically connected load, figured by Article 220 or another approved method, unless load management limits it.

Which code applies to my generator hookup in NJ?

The 2023 NEC took effect in NJ on August 17, 2026. Complete permit applications submitted by February 17, 2027 may still be reviewed under the previous code.

Do you install generators?